Dispute Management

Central Government Office Building

Service provided by:

Senior Programming Analyst

Client:

Joint Venture MEP Contractors

Task:

To demonstrate the cause and effect of the delay and disruption to the building services installation.

Solution:

Compile a graphical chart to give justification for the cause and effect.

Outcome:

The JV was granted the full extension of time and relate the actual costs incurred to the series of delay events that was presented.