	<title>Newsletter Archives - The Contracts Group</title>
	<atom:link href="https://contractsgroupltd.com/category/news/newsletter/feed/" rel="self" type="application/rss+xml" />
	<link></link>
	<description>Construction Claims, Contract &#38; Commercial Consultants Hong Kong &#124; The Contracts Group Ltd</description>
	<lastBuildDate>Thu, 12 Nov 2026 09:01:36 +0000</lastBuildDate>
	<language>en-US</language>
	<sy:updatePeriod>
	hourly	</sy:updatePeriod>
	<sy:updateFrequency>
	1	</sy:updateFrequency>
	<generator>https://wordpress.org/?v=7.1.5</generator>

<image>
	<url>https://contractsgroupltd.com/wp-content/uploads/2020/11/cropped-favicon-1-32x32.png</url>
	<title>Newsletter Archives - The Contracts Group</title>
	<link></link>
	<width>32</width>
	<height>32</height>
</image> 
	<item>
		<title>Pre-Dispute Readiness: Protecting Entitlement and Building the Project Record</title>
		<link>https://contractsgroupltd.com/pre-dispute-readiness-by-avan-fan-y-k-lam/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=pre-dispute-readiness-by-avan-fan-y-k-lam</link>
		
		<dc:creator><![CDATA[TCG]]></dc:creator>
		<pubDate>Tue, 11 Aug 2026 03:26:25 +0000</pubDate>
				<category><![CDATA[News]]></category>
		<category><![CDATA[Newsletter]]></category>
		<guid isPermaLink="false">https://contractsgroupltd.com/?p=5820</guid>

					<description><![CDATA[<p>Avan Fan and Y. K. Lam explain how timely notices, clear project records and early action can help teams manage emerging issues and protect their contractual position.</p>
<p>The post <a href="https://contractsgroupltd.com/pre-dispute-readiness-by-avan-fan-y-k-lam/">Pre-Dispute Readiness: Protecting Entitlement and Building the Project Record</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p><em>By Avan Fan and Y. K. Lam</em></p>
<p>Avan Fan and Y. K. Lam explain how timely notices, clear project records and early action can help teams manage emerging issues and protect their contractual position.</p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2026/08/Pre-Dispute_Readiness-R3.pdf">Read the English PDF</a></p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2026/08/Pre-Dispute_Readiness_Traditional_Chinese.pdf">Read the Chinese PDF</a></p>
<p>Pre-dispute readiness is not about manufacturing a future claim. It is about administering the contract properly, resolving issues while they remain manageable and preserving an objective record of what occurred.</p>
<p>Nobody signs a construction contract expecting to end up before a court or tribunal. Yet by the time a dispute crystallises, the parties’ positions may already have been materially affected by what they notified, recorded and administered while the relevant events were unfolding. In practice, recurring weaknesses include notices that were not issued, were issued late or did not comply with the contract, and records that are generic, fragmented or silent on the matters later put in issue.</p>
<p>Effective notices and records serve three connected purposes. They help the project team identify and manage issues at the time; they preserve contractual rights and support timely contractual responses; and, where a dispute cannot be avoided, they provide reliable evidence. The same disciplines apply to employers, contractors, subcontractors and consultants. Each party should be able to demonstrate its instructions, decisions, progress, costs, payments and responses to material events.</p>
<p>Four disciplines should therefore be established from the outset. They are sound project management practices in their own right and provide a reliable foundation for any subsequently appointed quantum or delay expert.</p>
<h2>1. Comply with the contractual notice regime</h2>
<p>In Obrascon Huarte Lain SA v Attorney General for Gibraltar [2014] EWHC 1028 (TCC), the parties accepted that the notice requirement in Sub-Clause 20.1 of the FIDIC Yellow Book operated as a condition precedent. The case does not establish a universal rule that every claim is lost whenever a notice provision is not followed: the effect depends on the wording of the contract, the governing law and the facts. The practical point is nevertheless clear. Where timely notice is a condition precedent, non-compliance may bar an otherwise valid claim.</p>
<p>Every event that may affect time, cost, quality, scope or contractual rights should trigger an immediate check of the contract. The team should identify what must be notified, by whom, to whom, in what form and within what period. It should also identify any continuing requirements, such as updates, particulars, supporting records or separate notices under related clauses.</p>
<p>Depending on the contract and project procedures, a well-maintained notice register should normally record:</p>
<ul>
<li>the event, instruction or circumstance giving rise to the notice;</li>
<li>the relevant contractual clause and deadline;</li>
<li>the person responsible for drafting, approving and issuing it;</li>
<li>the method and date of service, together with proof of receipt;</li>
<li>any required follow-up notices, particulars or substantiation; and</li>
<li>the response received and any resulting action.</li>
</ul>
<p>The register should be maintained in real time and reviewed at progress and commercial meetings. It is a simple control, but it can help preserve entitlement, support timely follow-up and provide an auditable record of contractual compliance. After twelve (12) years, the Privy Council in Uniform Building Contractors Ltd v Water and Sewerage Authority of Trinidad and Tobago [2026] UKPC 2 reinforced Sub-Clause 20.1 of the FIDIC Yellow Book as being in “classic condition precedent form” and applied it strictly by rejecting the argument that the Engineer&#39;s actual knowledge of the disputed work could substitute for the contractor&#39;s notice.</p>
<h2>2. Create accurate, specific contemporaneous records</h2>
<p>The quality of a project record is not measured by volume. A large document repository may still provide little assistance if its contents cannot be connected to a particular event, activity, location, resource or period. Useful records are created routinely, at or near the relevant time, and are sufficiently specific to explain what happened and what operational consequence followed.</p>
<p>Depending on the project and the issue, relevant records may include:</p>
<ul>
<li>daily progress reports, site diaries, photographs and marked-up drawings;</li>
<li>records of labour, plant, materials, idle resources and productivity;</li>
<li>cost ledgers, timesheets, invoices, payment records and resource-allocation sheets;</li>
<li>programmes, updates, progress measurements, narratives and change logs;</li>
<li>instructions, requests for information, inspection records, meeting minutes and correspondence; and</li>
<li>document-control data for email, messaging platforms and common data environments.</li>
</ul>
<p>Records should identify the date, location, activity, event and affected resources. They should be consistent across the programme, cost, site and correspondence systems, subject to an identified review or approval process, retained with proper version control and capable of efficient retrieval and cross-reference.</p>
<p>The decision in Van Oord UK Ltd v Allseas UK Ltd [2015] EWHC 3074 (TCC) illustrates how contemporaneous records may later be used to test the credibility of a claim. The absence of references to alleged standing time and disruption in detailed daily reports materially weakened the later claim. The lesson is not that site teams should write claims into their diaries. It is that daily records should neutrally describe the event, affected resources, location, activity, duration and actual operational consequence.</p>
<p>Similarly, Attorney General for the Falkland Islands v Gordon Forbes Construction (Falklands) Ltd [2003] BLR 280 confirms that witness evidence prepared after the event does not itself become a contemporaneous record and will not ordinarily cure the absence of records that the contract required to be maintained. Later evidence may explain an existing record, but it cannot recreate one that was never made. Record-keeping systems should therefore be established at project commencement and aligned with the contract&#39;s own requirements.</p>
<h2>3. Integrate cost, programme and site information</h2>
<p>Cost, programme and site information should not be maintained in isolation. The commercial records should identify where and when cost was incurred; the programme should show the activities and sequence affected; and the site records should explain what was actually occurring. The objective is a traceable chain from the relevant event to its effect on progress, resources and cost.</p>
<p>Practical controls include:</p>
<ul>
<li>a common coding structure across cost, programme and change records;</li>
<li>reconciliation of reported progress with site records and programme updates;</li>
<li>preservation of baseline, update and recovery programme versions;</li>
<li>documented changes to logic, sequencing, calendars and progress status;</li>
<li>resource and cost records that can be traced to activities, locations and periods; and</li>
<li>regular review of inconsistencies before they become embedded in the project record.</li>
</ul>
<p>In White Constructions Pty Ltd v PBS Holdings Pty Ltd [2019] NSWSC 1166, the court declined to treat either of two competing delay models as determinative. The fact that a methodology appeared in the Society of Construction Law Delay and Disruption Protocol did not give it special evidential status. Causation still required close examination of the contemporaneous project evidence, including the site records showing what was occurring and what was affecting progress.</p>
<p>The same principle applies to quantum evidence. Santos v Fluor [2025] QSC 184 illustrates the importance of matching an expert&#39;s discipline and experience to the issues in dispute. A quantity surveyor may be particularly well placed to address measurement, valuation and construction-cost issues, while an accountant may be better suited to accounting, financing or business-loss issues. Whatever the discipline, the analysis must be transparent, traceable and supported by reliable underlying records.</p>
<p>Methodology is a tool, not a substitute for evidence. An analysis should be selected because it is appropriate to the contractual question, the facts and the records available—not simply because it carries a recognised label.</p>
<h2>4. Assign clear responsibility for notices and records</h2>
<p>Pre-dispute readiness is a project-wide responsibility. It does not depend on a quantity surveyor, planner or claims professional carrying the entire burden, and responsibility should not be allowed to fall into the gaps between disciplines.</p>
<p>The contract should determine who is authorised to issue notices and other formal communications. The quantity surveyor or commercial team may identify, draft, track and substantiate notices, while maintaining cost, valuation and change records against a consistent coding structure. The planner should establish progress-data requirements, manage the programme development and updating process, document changes to logic and sequencing, preserve programme versions and reconcile reported progress with the underlying site evidence. Site management should produce accurate primary records of labour, plant, activities, conditions and events.</p>
<p>Document control should ensure that current and superseded versions, relevant metadata, correspondence and transmittals can be retrieved.</p>
<p>These responsibilities should be recorded in a project protocol or responsibility matrix and reviewed when personnel, systems or contractual arrangements change. The aim is not to build a partisan case for an expert to inherit. It is to preserve objective evidence from which an independent expert can form an independent opinion.</p>
<h2>A practical readiness check</h2>
<p>At regular project reviews, the team should be able to answer four questions:</p>
<ul>
<li>Have all material events been checked against the applicable notice requirements?</li>
<li>Do the records identify what happened, where, when, to which activities and with what effect?</li>
<li>Can the cost, programme and site information be reconciled to a common factual account?</li>
<li>Is responsibility for creating, reviewing, issuing and preserving each record clear?</li>
</ul>
<h2>Conclusion</h2>
<p>Effective pre-dispute readiness strengthens project administration while issues remain capable of being managed and preserves an objective account of what occurred. Clear responsibilities, compliant notices, integrated cost and programme information and disciplined document control improve project decision-making and provide a reliable foundation if a dispute later requires expert analysis or formal determination. Sound analysis remains essential, but it cannot compensate for an unreliable factual foundation.</p>
<p>For practical assistance with an emerging construction disagreement, explore our <a href="https://contractsgroupltd.com/services/dispute-avoidance-early-resolution/" style="text-decoration:underline;text-underline-offset:3px;">dispute avoidance and early resolution</a> services, including independent peer reviews and assessments of contractual positions.</p>
<p>The post <a href="https://contractsgroupltd.com/pre-dispute-readiness-by-avan-fan-y-k-lam/">Pre-Dispute Readiness: Protecting Entitlement and Building the Project Record</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></content:encoded>
					
		
		
			</item>
		<item>
		<title>15th Anniversary Newsletter: Hong Kong Construction Market and Contract Update</title>
		<link>https://contractsgroupltd.com/15th-anniversary-edition/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=15th-anniversary-edition</link>
		
		<dc:creator><![CDATA[TCG]]></dc:creator>
		<pubDate>Tue, 07 Jul 2026 05:37:15 +0000</pubDate>
				<category><![CDATA[News]]></category>
		<category><![CDATA[Newsletter]]></category>
		<guid isPermaLink="false">https://contractsgroupltd.com/?p=5758</guid>

					<description><![CDATA[<p>This edition brings together Hong Kong construction market statistics, project news and Summer Lo's review of the 2025 HKIS Standard Form of Building Contracts.</p>
<p>The post <a href="https://contractsgroupltd.com/15th-anniversary-edition/">15th Anniversary Newsletter: Hong Kong Construction Market and Contract Update</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p>This edition brings together Hong Kong construction market statistics, project news and Summer Lo&#39;s review of the 2025 HKIS Standard Form of Building Contracts.</p>
<h2>Hong Kong Construction Market: First Quarter of 2026</h2>
<p>The newsletter reports that the gross value of construction work performed by main contractors reached HK$72.7 billion in the first quarter of 2026, up 2.9% year on year, or 1.0% after adjusting for price changes. Public sector site work rose 17.8% in nominal terms to HK$35.9 billion, while private sector site work fell 15.9% to HK$16.5 billion.</p>
<h2>Project News</h2>
<ul>
<li><strong>San Tin Technopole:</strong> The edition covers the award of a HK$2.27 billion site formation and infrastructure contract to the CRBC–Maylon Joint Venture. The works include road connections, a sewage pumping station and associated infrastructure.</li>
<li><strong>Kwai Chung logistics development:</strong> The edition reports on the HK$3.6 billion contract awarded to CR Construction for a cold storage and logistics development for Chinachem and ESR Group.</li>
</ul>
<h2>2025 HKIS Standard Form of Building Contracts: Three Changes to Review</h2>
<p><em>From Summer Lo&#39;s feature article</em></p>
<p>Summer Lo looks at what the 2025 edition means for quantity surveyors and other construction practitioners. Her review focuses on three changes:</p>
<ol>
<li><strong>Alignment with the Security of Payment Ordinance:</strong> The article examines how the new form addresses payment administration, adjudication and conditional payment provisions.</li>
<li><strong>A coordinated suite of contracts:</strong> The updated main contract, nominated subcontract and nominated supply contract are designed to work together. The article explains why consistent definitions, procedures and risk allocation matter across the supply chain.</li>
<li><strong>One framework for contracts with or without bills of quantities:</strong> The article explains how the combined form brings the choice of quantity arrangements into the same framework, and why design maturity and the tender documents matter to that choice.</li>
</ol>
<p>The full feature also discusses the Base Date and practical considerations for payment administration, project records, supply chain due diligence and procurement advice.</p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2026/07/20260618-TCG15-newsletter-English.pdf">Read the English PDF</a></p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2026/07/20260618-TCG15-newsletter-Chinese.pdf">Read the Chinese PDF</a></p>
<p>Related service: <a href="https://contractsgroupltd.com/services/contract-advisory/" style="text-decoration:underline;text-underline-offset:3px;">Contract Advisory Services</a>.</p>
<p>The post <a href="https://contractsgroupltd.com/15th-anniversary-edition/">15th Anniversary Newsletter: Hong Kong Construction Market and Contract Update</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></content:encoded>
					
		
		
			</item>
		<item>
		<title>Newsletter – Let&#039;s Talk Earned Value Management</title>
		<link>https://contractsgroupltd.com/newsletter-lets-talk-earned-value-management/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=newsletter-lets-talk-earned-value-management</link>
		
		<dc:creator><![CDATA[TCG]]></dc:creator>
		<pubDate>Wed, 11 Mar 2026 03:39:21 +0000</pubDate>
				<category><![CDATA[Newsletter]]></category>
		<guid isPermaLink="false">https://contractsgroupltd.com/?p=5655</guid>

					<description><![CDATA[<p>Earned Value Management compares what was planned, what was delivered and what it cost, helping project teams spot when progress and spending tell different stories.</p>
<p>The post <a href="https://contractsgroupltd.com/newsletter-lets-talk-earned-value-management/">Newsletter – Let&#039;s Talk Earned Value Management</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p>It&#39;s simply a project performance measuring tool that shows whether the work done is keeping up with the money spent. That&#39;s all Earned Value Management (EVM) does, it compares what you planned, what you achieved, and what you spent to show whether your project is performing well or not.</p>
<p>If you&#39;ve spent long enough in project controls, you&#39;ll know that schedules and cost reports often tell different stories. The planner says we&#39;re on track; the quantity surveyor says we are burning cash too fast. Somewhere between the two, lies the truth; enters &#8211; Earned Value Management (EVM).</p>
<p><a href="https://www.linkedin.com/pulse/lets-talk-earned-value-managment-the-contracts-group-limited-yojxc/?trackingId=zQ3%2ByCNkS1W2XSByrhzIDA%3D%3D"><strong>Read more</strong></a></p>
<h2>Earned Value Management: Web Overview</h2>
<p><em>Feature by Rahul Pun</em></p>
<h3>What Earned Value Management measures</h3>
<p>Earned Value Management gives planners, quantity surveyors and project managers a common way to compare progress and cost at the same reporting date. Planned Value is the budgeted value of work scheduled by that date. Earned Value is the budgeted value of work actually completed. Actual Cost is what was spent to complete that work.</p>
<h3>What to do when the measures diverge</h3>
<p>If earned value is below planned value, the team has completed less work than planned. If actual cost is above earned value, it has spent more than budgeted for the work completed. These comparisons help teams spot deterioration early, investigate the causes and discuss whether forecasts or corrective actions need to change.</p>
<h3>Putting the measures to work in Primavera P6</h3>
<p>Rahul recommends building a realistic, resource- and cost-loaded programme, setting a baseline and keeping progress and cost data current. With the right inputs and configuration, P6 can track earned value and report schedule and cost performance indicators. The measures are most useful when the team agrees how progress is measured and reviews the results together.</p>
<p>The original LinkedIn edition also includes project and staff news and a Chinese version.</p>
<p>The post <a href="https://contractsgroupltd.com/newsletter-lets-talk-earned-value-management/">Newsletter – Let&#039;s Talk Earned Value Management</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></content:encoded>
					
		
		
			</item>
		<item>
		<title>Newsletter – Do We Need to Keep Subcontractors in the Dark?</title>
		<link>https://contractsgroupltd.com/newsletter-do-we-need-to-keep-subcontractors-in-the-dark/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=newsletter-do-we-need-to-keep-subcontractors-in-the-dark</link>
		
		<dc:creator><![CDATA[TCG]]></dc:creator>
		<pubDate>Wed, 25 Feb 2026 05:56:54 +0000</pubDate>
				<category><![CDATA[Newsletter]]></category>
		<guid isPermaLink="false">https://contractsgroupltd.com/?p=5608</guid>

					<description><![CDATA[<p>Avan Fan examines whether main contractors should share their master programmes with subcontractors and what withholding programme information can mean for delay claims.</p>
<p>The post <a href="https://contractsgroupltd.com/newsletter-do-we-need-to-keep-subcontractors-in-the-dark/">Newsletter – Do We Need to Keep Subcontractors in the Dark?</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p><em>By Avan Fan</em></p>
<p>It is a common practice for Main Contractors to withhold full Master Programmes from subcontractors to limit delay claims. But is this legally sound?</p>
<p>Read the full newsletter thru below link.</p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2026/02/Do-we-need-to-keep-subbies-in-the-dark-english.pdf">Do we need to keep subcontractors in the dark?  </a></p>
<h2>Read the Article</h2>
<p>In most of the standard forms of sub-contracts used in the Hong Kong construction industry there is an obligation for subcontractors to carry out their works to suit the Main Contractor&#39;s programme. Contrary to this obligation, it seems that Main Contractors like to keep their subcontractors in the dark by not providing the full version of the Master Programme or any updated revisions, most likely this is so that the subcontractors are prevented from claiming for extension of time because of delays by other subcontractors or even the Main Contractor. The reasonableness of this practice is questionable.</p>
<h3>The Case:</h3>
<p>The Australian case Alstom v Yokogawa Australia Pty Ltd &amp; Anor (No.7) [2012] SASC 49 may be able to answer this question.</p>
<p>Alstom was the Main Contractor and Yokogawa Australia Pty Ltd &amp; Anor (also known as YDRML) was its subcontractor responsible for the electrical, control and instrumentation Works of the refurbishment and automation of the Playford B Power Station. YDRML&#39;s sub-contract amount was AUD33.8M which was roughly a quarter of the Main Contract amount.</p>
<p>Similar to the situation described in my previous article on back-to-back contracts ('Formation of Construction Contract &#8211; Handle with Care (Part I)'), Alstom used the Main Contract as a template for the subcontract. Instead of drafting a bespoke agreement, they modified the Main Contract with special conditions to alter certain definitions and terms. The project was in significant delay and the client withheld AUD 13M in liquidated damages from Alstom.</p>
<p>In the apportionment of the delay liabilities, the question was whether Alstom was required to provide its updated and accurate works programme showing all relevant logic links to YDRML, notwithstanding that there was no express contractual provision to that effect. If it is the case here, YDRML would not be liable for the delays.</p>
<p>There were many thousands of activities to be scheduled, therefore a Master Programme was produced to assist in determining the order and timing of the activities, and to enable forward planning. In a project, most activities have “predecessors” – these are simply other tasks that must be completed or started before the current task can begin. For example, if activity “X” is excavation, one of the predecessor activities may be the lateral support.</p>
<p>In this project, the software specified in the Main Contract was Primavera P3. Like other programming software, P3 has the ability to dynamically recalculate the critical path and work out the effect on a Milestone date of any delay that occurred during the course of the Works. It is not unusual no matter whether in Hong Kong or Australia, that the Main Contractors rarely shares all of their planning information with its subcontractors. Even if it is being shared, it is usually and deliberately in the form of PDF printouts, rather than Primavera or Microsoft Project file form so that the subcontractors cannot know about the logic lying behind whatever the Main Contractors are demanding by way of performance. Worse still, many Main Contractors only provide their subcontractors with extracts from the Master Programme showing only the activities and corresponding start and finish dates relevant to that particular subcontractor.</p>
<p>Returning to the case, in many instances, Alstom refused to provide to YDRML the electronic form of its Primavera programme. It was always the case that Alstom gave YDRML extracts from its Master Programme, showing only selected portions Alstom thought were relevant to YDRML&#39;s activities. In the main part, the extracts omitted the time relationship links between activities and their predecessors. In the court, it was found that Alstom&#39;s Master Programme was inadequate, the Milestone dates had been entered as fixed dates and consequently, could not move forward when delays were incorporated into the Master Programme.</p>
<h3>The Court&#39;s Findings:</h3>
<p>The Court found that there were “thousands” of activities that YDRML was unable to properly schedule without knowing the predecessors to them or when Alstom would give access. There were three legal principles that resulted in an obligation on Alstom as the Main Contractor to provide sufficient information to YDRML to enable it to plan and work according to the plan:</p>
<p>1. Unless the contract expressly says otherwise, there is an implied duty to co-operate resting on both parties; 2. Every commercial contract includes an implied obligation to act in good faith; 3. Unless the contract expressly says otherwise, if any act by one party prevents the other from proceeding as planned, the innocent party will be deemed to have performed the contract.</p>
<h3>Duty to Act in Good Faith:</h3>
<p>The Court went on to discuss whether there is an implied duty to act in good faith. It held that the obligation to cooperate and the obligation to act in good faith extended to a requirement to provide to YDRML the full electronic version of Alstom&#39;s Primavera program, including any updated versions during the Works. Alstom&#39;s failure to do so had prevented YDRML from performing its obligations under the sub-contract – an act of prevention, therefore, YDRML was not liable for any of the delays and therefore not liable for any portion of liquidated damages.</p>
<h3>Some Thoughts:</h3>
<p>Some of the reasons for Main Contractors not providing comprehensive delay information as well as the full Primavera programme to their subcontractors is as follows:</p>
<ul>
<li>Prevent pacing delays – the subcontractors may slow down as well;</li>
<li>Avoid the subcontractors claiming for EOTs when the Main Contractor is not yet confident to get the same from the client;</li>
<li>Maximise their returns and generate more float for the project;</li>
<li>Any subsequent acceleration of the works by the subcontractors can be masked and remain unrewarded.</li>
</ul>
<p>Despite the fact that keeping the subcontractors in the dark enjoys a lot of benefits for the Main Contractor, Main Contractors should now be aware that following this case, more subcontractors may be willing to go to the court to challenge the Main Contractor, especially when issues related to LD&#39;s/prolongation costs arise.</p>
<p>Under the NEC Contract, although the NEC Contract does not use the term good faith, the court in the case of Van Oord UK Ltd v Dragados UK Ltd [2021] CSIH 50 concerning an NEC sub-contract, the court commented that “Clause 10.1 is not merely an avowal of aspiration, instead, it reflects and reinforces the general principle of good faith in contract.”</p>
<p>In short, providing the updated Master Programmes in Primavera or MS project formats to the subcontractors is easy, as it can prevent the argument of prevention and later disputes. However, one wonders whether that will make any difference to Main Contractor&#39;s in the future, old habits still prevail.</p>
<p>The post <a href="https://contractsgroupltd.com/newsletter-do-we-need-to-keep-subcontractors-in-the-dark/">Newsletter – Do We Need to Keep Subcontractors in the Dark?</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></content:encoded>
					
		
		
			</item>
		<item>
		<title>Newsletter &#8211; Mindset</title>
		<link>https://contractsgroupltd.com/newsletter-mindset/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=newsletter-mindset</link>
		
		<dc:creator><![CDATA[TCG]]></dc:creator>
		<pubDate>Thu, 30 Oct 2025 07:10:43 +0000</pubDate>
				<category><![CDATA[Newsletter]]></category>
		<guid isPermaLink="false">https://contractsgroupltd.com/?p=5319</guid>

					<description><![CDATA[<p>Explore the topic of mindset in this edition of The Contracts Group newsletter.</p>
<p>The post <a href="https://contractsgroupltd.com/newsletter-mindset/">Newsletter &#8211; Mindset</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p>Newsletter in English and Chinese version</p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2025/10/MindsetEnglishVersion.pdf">English Version</a></p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2025/10/MindsetChineseVersion.pdf">Chinese Version</a></p>
<h2>Mindset: The Feature Article</h2>
<p>By Colin Lee</p>
<p>With the increasing number of projects currently using one of the NEC Suites of Contract, and likely to be on the increase over the coming years, one significant question which arises is whether the Hong Kong Construction Industry is able to handle these forms of contract, which are vastly different from the Standard Forms of Contract everyone is familiar with whether civil, building or Government Forms, having used such Forms for so many years. The fundamental basis of the NEC Forms is mutual trust and co-operation, both of which are sadly missing from the current practices in the Hong Kong Construction Industry wherein neither trust nor co-operation exist on most projects, whilst there are exceptions from time to time. For the NEC Forms of Contract to work as designed requires a complete change of mindset in the Construction Industry in Hong Kong, both within the Companies and the individuals who represent them on the various projects.</p>
<p>So, what do we mean by mindset? Wikipedia provides a good explanation:</p>
<p>‘A mindset refers to an established set of attitudes of a person or group concerning culture, values, philosophy, frame of reference, outlook or disposition. It may also arise from a person&#39;s worldviews or beliefs about the meaning of life.’</p>
<p>With this description in mind how do we go about changing both Company and individual mindset, some suggested thoughts follow:</p>
<ul>
<li>There must be a willingness for change in the first instance.</li>
<li>Communicate the purpose and benefits of the change and explain why the change is necessary</li>
<li>Model the behaviour you want to see in your team, show them that you are open to learning, experimenting and improving. Leading by example is one of the most powerful enforcers of change.</li>
<li>Identify the roadblocks to change and how to overcome them.</li>
<li>Address resistance and negativity to change in your team and work together to find a way to agree the way forward.</li>
<li>Build trust and rapport in your team, allow feedback without any repercussions.</li>
<li>Understand that change is not a one-time event, but a continuous process that requires constant monitoring and improvement</li>
</ul>
<p>No doubt there are many other thoughts as to how to change mindset, all of which sounds good, but how do we put them into practice in the environment currently found in the Construction Industry in Hong Kong? In the writer&#39;s opinion, this has to start from within the various Employers, Consultancies and Contractor organisations who need to set the targets for their staff to follow.</p>
<p>As it stands at the present time, whilst there have been some examples of projects being successfully completed using the NEC Suite of Contracts, there are more projects which have failed and continue to fail for various reasons, mainly because everyone tends to revert to the ways they have always carried out projects i.e., contentiously, which is not how the NEC is intended to work.</p>
<p>This is a sad indictment of the construction industry as it currently stands, most of the complaints we hear about are from the Contractors, in particular, the delayed process of achieving an accepted programme, which is fundamental under NEC and finalizing compensation events within specified timeframes, which is being ignored throughout the process. Actually, this is, in fact, endemic in the industry today with the valuation of variations, extensions of time being disputed and Master Programmes under the standard forms of contract never being finalized until months after the project has commenced thereby making them redundant by the time they are agreed.</p>
<p>Unless there is a sustained effort within the industry to change the mindset and not continue to revert to the old ways of handling projects, NEC will eventually go the way of every other form of contract which has failed to date i.e., for example, Partnering, which is fundamentally similar to the NEC, which just died a death and disappeared.</p>
<p>The writer looks forward to hearing from our readers as to their impressions of what is needed to change the mindset here in Hong Kong and how to implement the same.</p>
<p>The post <a href="https://contractsgroupltd.com/newsletter-mindset/">Newsletter &#8211; Mindset</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></content:encoded>
					
		
		
			</item>
		<item>
		<title>Formation of Construction Contract &#8211; Handle with Care Part II</title>
		<link>https://contractsgroupltd.com/formation-of-construction-contract-handle-with-care-part-ii/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=formation-of-construction-contract-handle-with-care-part-ii</link>
		
		<dc:creator><![CDATA[TCG]]></dc:creator>
		<pubDate>Tue, 28 Oct 2025 10:02:45 +0000</pubDate>
				<category><![CDATA[Newsletter]]></category>
		<guid isPermaLink="false">https://contractsgroupltd.com/?p=5293</guid>

					<description><![CDATA[<p>The second instalment of our newsletter series on the formation of construction contracts.</p>
<p>The post <a href="https://contractsgroupltd.com/formation-of-construction-contract-handle-with-care-part-ii/">Formation of Construction Contract &#8211; Handle with Care Part II</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p><img decoding="async" class="wp-image-5294 aligncenter" src="https://contractsgroupltd.com/wp-content/uploads/2025/10/battlegraphics.jpg" alt="" width="256" height="159" srcset="https://contractsgroupltd.com/wp-content/uploads/2025/10/battlegraphics.jpg 469w, https://contractsgroupltd.com/wp-content/uploads/2025/10/battlegraphics-300x186.jpg 300w" sizes="(max-width: 256px) 100vw, 256px" /></p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2025/10/FinalEngVersionJuly2025.pdf">English version newsletter</a></p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2025/10/202507-newsletterChinese-version.pdf">Chinese version newsletter</a></p>
<p>&nbsp;</p>
<h2>Formation of Construction Contract: The Feature Article</h2>
<p>This article is the second part of the captioned topic. In Part I, we reviewed the contractual issues surrounding the incorporation of an Arbitration Clause into a Sub-Contract. In Part II, we now consider the contractual issues related to the “Battle of the Forms” and provide practical recommendations.</p>
<h3>Battle of the Forms</h3>
<p>Under common law, the traditional “mirror image” rule surrounding offer and acceptance requires that an acceptance must match the offer for a contract to be formed, whereas in disputes concerning the “Battle of the Forms”, the “last shot” rule applies. However, it is common for parties involved in a project to commence performance—such as initiating work or delivering materials—without a clear agreement on which terms govern the project, often resulting in disputes.</p>
<p>Battle of the forms disputes can lead to unexpected outcomes, in particular, where the parties have failed to agree as to which set of terms governs their relationship. A recent case of Caledonia Water Alliance v Electrosteel Casting [2024] CSOH87, dealt with this issue. This was a battle as to which of the respective parties’ own standard terms and conditions (T&amp;Cs) applied. Surprisingly, the court undertook an objective consideration of what had been communicated between the parties by words and action and determined that the overarching NEC3 Framework Contract applied.</p>
<h3>The Facts</h3>
<p>In June 2015, Scottish Water (the Client) entered into an Alliance Agreement with the Caledonia Water Alliance, a joint venture, for the design and installation of water pipes for a project known as the South Edinburgh Resilience Scheme (“SERS”). This Agreement was based on the NEC3 Option C (Target Contract) terms. The Agreement obliged CWA, subject to certain conditions, to obtain items of plant, material and services from suppliers with whom Scottish Water had agreed contracts under an overarching framework (i.e., NEC3 Contracts).</p>
<p>In February 2016, Electrosteel (a pipework subcontractor) entered into a framework agreement with Scottish Water, the purpose of which was to allow Scottish Water or those working for it such as CWA to order plant and materials from them on the basis of pre-agreed terms and prices set out in the Framework Agreement. The Framework Agreement included a copy of Scottish Water&#39;s Terms and Conditions of Contract for the Purchase of Goods and Services under a Framework Agreement (the “SWT&amp;Cs”) which were expressly intended to govern all orders issued under the Framework Agreement.</p>
<p>Between June 2018 and May 2022, CWA placed sixty (60) orders with Electrosteel for ductile iron pipes for the SERS project. Each order was made via a purchase order from CWA followed by an order confirmation from Electrosteel. Both the purchase orders and the order confirmations contained standard wording seeking to incorporate each party&#39;s standard terms and conditions. A dispute arose over whether either of these terms and conditions applied in preference to the SWT&amp;Cs required by the Framework Agreement.</p>
<h3>The Scottish Court&#39;s Decision</h3>
<p>Based on the following key points, the Scottish Court determined that the SWT&amp;Cs applied to the contracts:</p>
<p>a) Awareness of framework terms:</p>
<p>Both parties (i.e., CWA and Electrosteel) demonstrated a clear understanding that their contractual relationship was to be governed by the NEC3 Framework Agreement, which included the SWT&amp;Cs. This mutual awareness was further evidenced by a “Supplier Guide” prepared by Electrosteel which explicitly confirmed that the Framework Agreement had been awarded without any amendments or deviations from the SWT&amp;Cs.</p>
<p>This reinforced the mutual expectation that the SWT&amp;Cs would comprehensively regulate the contractual obligations and commercial arrangements between the parties.</p>
<p>b) Objective consideration of party communications:</p>
<p>The Court adopted an objective approach in evaluating the communications and conduct of the parties throughout the course of their dealings. This assessment encompassed the initial establishment of the commercial relationship, the exchange of purchase orders and corresponding order confirmations, and the consistent reference to the SERS project and Scottish Water.</p>
<p>Although each party&#39;s documentation made reference to their respective standard terms and conditions, there was no substantive evidence to suggest an intention by either party to depart from the agreed SWT&amp;Cs under the Framework Agreement.</p>
<p>The Court further acknowledged that the routine inclusion of standard terms within contractual documentation is a common and accepted practice within the industry, and such inclusion alone did not constitute an intention to supersede or override the governing Framework Agreement.</p>
<p>c) Party actions under the Framework Agreement:</p>
<p>Electrosteel&#39;s invoices consistently referenced a dedicated account number that had been specifically established for transactions conducted under the Scottish Water Framework Agreement. This administrative measure demonstrated alignment with the contractual framework and further reinforced the parties’ adherence to its terms.</p>
<p>In addition, Electrosteel made rebate payments to Scottish Water in accordance with the obligations set out under the Framework Agreement, further evidencing its implementation and recognition as the governing contractual instrument for the transactions in question.</p>
<p>d) Common purpose:</p>
<p>The Court also noted that its interpretation was supported by the parties’ joint purpose to participate in Scottish Water&#39;s framework arrangement. This purpose supported the application of the SWT&amp;Cs as intended by the Framework Agreement.</p>
<p>The Court further observed that its interpretation was consistent with the shared commercial objective of both parties to participate in Scottish Water&#39;s framework arrangement. This mutual purpose provided contextual support for the application of the Standard Terms and Conditions (SWT&amp;Cs) as set out in the NEC3 Framework Agreement. The parties’ alignment with the overarching framework reinforced the conclusion that the SWT&amp;Cs were intended to govern their contractual relationship.</p>
<h3>Recommendations for Good Practices</h3>
<p>1. In the case of the “Battle of the Forms”, the ‘last shot’ rules usually apply, except where the communications between the parties by words and actions suggest other things.</p>
<p>2. Clear Communication: This applies to both the issue of the “Battle of the Forms” and “Back-to- Back” provisions. All terms should be clearly communicated and acknowledged. With the advancement of technology, it is easy to provide the soft copy of the main contract and any other related documents.</p>
<p>3. Clear words should be used if the sub-contract or sub-sub-contract is intended to adopt the same dispute resolution mechanism as the main contract.</p>
<p>The post <a href="https://contractsgroupltd.com/formation-of-construction-contract-handle-with-care-part-ii/">Formation of Construction Contract &#8211; Handle with Care Part II</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></content:encoded>
					
		
		
			</item>
		<item>
		<title>Formation of Construction Contract &#8211; Handle with Care (Part 1) &#8211; June 2025</title>
		<link>https://contractsgroupltd.com/formation-of-construction-contract-handle-with-care-part-1-june-2025/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=formation-of-construction-contract-handle-with-care-part-1-june-2025</link>
		
		<dc:creator><![CDATA[TCG]]></dc:creator>
		<pubDate>Tue, 30 Sep 2025 08:21:06 +0000</pubDate>
				<category><![CDATA[Newsletter]]></category>
		<guid isPermaLink="false">https://contractsgroupltd.com/?p=5251</guid>

					<description><![CDATA[<p>The first instalment of our newsletter series on the formation of construction contracts.</p>
<p>The post <a href="https://contractsgroupltd.com/formation-of-construction-contract-handle-with-care-part-1-june-2025/">Formation of Construction Contract &#8211; Handle with Care (Part 1) &#8211; June 2025</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p><a href="https://contractsgroupltd.com/wp-content/uploads/2025/09/202503Engnewsletter.pdf">English version</a></p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2025/09/202507-newsletterChinese-version.pdf">Chinese version</a></p>
<p>&nbsp;</p>
<p>The post <a href="https://contractsgroupltd.com/formation-of-construction-contract-handle-with-care-part-1-june-2025/">Formation of Construction Contract &#8211; Handle with Care (Part 1) &#8211; June 2025</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></content:encoded>
					
		
		
			</item>
		<item>
		<title>Ten Q&#038;A about the Construction Industry Security of Payment Ordinance in Hong Kong &#8211; March 2025</title>
		<link>https://contractsgroupltd.com/march-2025-newsletter/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=march-2025-newsletter</link>
		
		<dc:creator><![CDATA[TCG]]></dc:creator>
		<pubDate>Tue, 30 Sep 2025 06:17:57 +0000</pubDate>
				<category><![CDATA[Newsletter]]></category>
		<guid isPermaLink="false">https://contractsgroupltd.com/?p=5242</guid>

					<description><![CDATA[<p>Ten questions and answers about Hong Kong's Construction Industry Security of Payment Ordinance.</p>
<p>The post <a href="https://contractsgroupltd.com/march-2025-newsletter/">Ten Q&#038;A about the Construction Industry Security of Payment Ordinance in Hong Kong &#8211; March 2025</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p>&nbsp;</p>
<p>&nbsp;</p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2025/09/202503Engnewsletter.pdf">English version</a></p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2025/09/202503Engnewsletter.pdf">Chinese version</a></p>
<p>&nbsp;</p>
<p>The post <a href="https://contractsgroupltd.com/march-2025-newsletter/">Ten Q&#038;A about the Construction Industry Security of Payment Ordinance in Hong Kong &#8211; March 2025</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></content:encoded>
					
		
		
			</item>
		<item>
		<title>Collateral warranties and the ability to adjudicate</title>
		<link>https://contractsgroupltd.com/collateral-warranties-and-the-ability-to-adjudicate/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=collateral-warranties-and-the-ability-to-adjudicate</link>
		
		<dc:creator><![CDATA[TCG]]></dc:creator>
		<pubDate>Thu, 06 Feb 2025 02:04:34 +0000</pubDate>
				<category><![CDATA[Newsletter]]></category>
		<guid isPermaLink="false">https://contractsgroupltd.com/?p=5018</guid>

					<description><![CDATA[<p>This newsletter examines collateral warranties and how they can affect the ability to adjudicate.</p>
<p>The post <a href="https://contractsgroupltd.com/collateral-warranties-and-the-ability-to-adjudicate/">Collateral warranties and the ability to adjudicate</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p><img fetchpriority="high" decoding="async" class="alignnone wp-image-5020" src="https://contractsgroupltd.com/wp-content/uploads/2025/02/Jan-2025-newsletter-headline-graphic-01-scaled.jpg" alt="" width="444" height="234" srcset="https://contractsgroupltd.com/wp-content/uploads/2025/02/Jan-2025-newsletter-headline-graphic-01-scaled.jpg 2560w, https://contractsgroupltd.com/wp-content/uploads/2025/02/Jan-2025-newsletter-headline-graphic-01-300x158.jpg 300w, https://contractsgroupltd.com/wp-content/uploads/2025/02/Jan-2025-newsletter-headline-graphic-01-1024x539.jpg 1024w, https://contractsgroupltd.com/wp-content/uploads/2025/02/Jan-2025-newsletter-headline-graphic-01-768x404.jpg 768w, https://contractsgroupltd.com/wp-content/uploads/2025/02/Jan-2025-newsletter-headline-graphic-01-1536x808.jpg 1536w, https://contractsgroupltd.com/wp-content/uploads/2025/02/Jan-2025-newsletter-headline-graphic-01-2048x1078.jpg 2048w" sizes="(max-width: 444px) 100vw, 444px" /></p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2025/02/Jan-2025-newsletter-01-scaled.jpg">Jan 2025 Newsletter in English </a></p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2025/02/Jan-2025-newsletter-02-scaled.jpg">Jan 2025 Newsletter in Chinese</a></p>
<p>The post <a href="https://contractsgroupltd.com/collateral-warranties-and-the-ability-to-adjudicate/">Collateral warranties and the ability to adjudicate</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></content:encoded>
					
		
		
			</item>
		<item>
		<title>Legal Lingo Illuminated: 10 Latin Phrases in Construction Disputes &#8211; December 2024</title>
		<link>https://contractsgroupltd.com/legal-lingo-illuminated-10-latin-phrases-in-construction-disputes-december-2024/?utm_source=rss&#038;utm_medium=rss&#038;utm_campaign=legal-lingo-illuminated-10-latin-phrases-in-construction-disputes-december-2024</link>
		
		<dc:creator><![CDATA[TCG]]></dc:creator>
		<pubDate>Tue, 28 Jan 2025 06:23:26 +0000</pubDate>
				<category><![CDATA[Newsletter]]></category>
		<guid isPermaLink="false">https://contractsgroupltd.com/?p=5002</guid>

					<description><![CDATA[<p>A guide to ten Latin phrases that readers may encounter in construction disputes.</p>
<p>The post <a href="https://contractsgroupltd.com/legal-lingo-illuminated-10-latin-phrases-in-construction-disputes-december-2024/">Legal Lingo Illuminated: 10 Latin Phrases in Construction Disputes &#8211; December 2024</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></description>
										<content:encoded><![CDATA[<p><img decoding="async" class="alignnone wp-image-5011" src="https://contractsgroupltd.com/wp-content/uploads/2025/01/original-christmas-2025-JJ-full-size-copy-01.jpg" alt="" width="359" height="292" srcset="https://contractsgroupltd.com/wp-content/uploads/2025/01/original-christmas-2025-JJ-full-size-copy-01.jpg 1577w, https://contractsgroupltd.com/wp-content/uploads/2025/01/original-christmas-2025-JJ-full-size-copy-01-300x244.jpg 300w, https://contractsgroupltd.com/wp-content/uploads/2025/01/original-christmas-2025-JJ-full-size-copy-01-1024x834.jpg 1024w, https://contractsgroupltd.com/wp-content/uploads/2025/01/original-christmas-2025-JJ-full-size-copy-01-768x626.jpg 768w, https://contractsgroupltd.com/wp-content/uploads/2025/01/original-christmas-2025-JJ-full-size-copy-01-1536x1252.jpg 1536w" sizes="(max-width: 359px) 100vw, 359px" /></p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2024/12/contracts-group-logo-copy.pdf">Dec 2024 Newsletter (English version)</a></p>
<p><a href="https://contractsgroupltd.com/wp-content/uploads/2025/01/Dec-2024-newsletter-chi.pdf">Dec 2024 Newsletter (Chinese version) </a></p>
<p>The post <a href="https://contractsgroupltd.com/legal-lingo-illuminated-10-latin-phrases-in-construction-disputes-december-2024/">Legal Lingo Illuminated: 10 Latin Phrases in Construction Disputes &#8211; December 2024</a> appeared first on <a href="https://contractsgroupltd.com">The Contracts Group</a>.</p>
]]></content:encoded>
					
		
		