Power Plant Facility, Hong Kong
Service provided by:
Associate Director
Project:
Power Plant Facility
Client:
Engineering Consultant
Task:
Provide contractual advice, provide estimates of the likely recovery and assist the consultant to substantiate claims for additional services it had performed during the course of the Project.
Solution:
TCGL worked closely with the client's project team to develop documents to concisely explain the background to each claim, the chronology of events giving rise to the claim and provide supporting information and explanations in respect to the hours assigned to the additional services claimed. This was challenging given records were not readily available and many of the project team had moved onto other projects.
Outcome:
An Additional Services submission was produced for each claim for onward submission/discussion with the Employer.
Related Case Studies
Ventria Residence, Hong Kong
The Employer was satisfied on facts that were demonstrated on a clear delay analysis presentation…
Contract No. 12/WSD/06
Successful negotiations between parties leading to the settlement of accounts.
MTRC XRL Contract 824
The prospect of the independent Expert providing opinion on unresolved matters led to a large…
Central Government Office Building
The JV was granted the full extension of time and relate the actual costs incurred…
Construction of Liangtang/ Heung Yuen Wan Boundary Control Point BCP Buildings and Associated Facilities
Successful negotiations between the Main Contractor and the Employer leading to settlement of claims.
Regional Fast Rail Project
The variations and claims submissions by the Main Contractors' team facilitated the amicable negotiation and…