Power Plant Facility, Hong Kong

Service provided by:

Associate Director

Project:

Power Plant Facility

Client:

Engineering Consultant

Task:

Provide contractual advice, provide estimates of the likely recovery and assist the consultant to substantiate claims for additional services it had performed during the course of the Project.

Solution:

TCGL worked closely with the client's project team to develop documents to concisely explain the background to each claim, the chronology of events giving rise to the claim and provide supporting information and explanations in respect to the hours assigned to the additional services claimed. This was challenging given records were not readily available and many of the project team had moved onto other projects.

Outcome:

An Additional Services submission was produced for each claim for onward submission/discussion with the Employer.

Ventria Residence, Hong Kong

The Employer was satisfied on facts that were demonstrated on a clear delay analysis presentation…

Read More

Contract No. 12/WSD/06

Successful negotiations between parties leading to the settlement of accounts.

Read More

MTRC XRL Contract 824

The prospect of the independent Expert providing opinion on unresolved matters led to a large…

Read More

Central Government Office Building

The JV was granted the full extension of time and relate the actual costs incurred…

Read More

Construction of Liangtang/ Heung Yuen Wan Boundary Control Point BCP Buildings and Associated Facilities

Successful negotiations between the Main Contractor and the Employer leading to settlement of claims.

Read More

Regional Fast Rail Project

The variations and claims submissions by the Main Contractors' team facilitated the amicable negotiation and…

Read More
Back To Top